It has definitely been busy this week at Garfield!

Bulk Plan and Sheathing inspections are scheduled for early next week since the South Duplex is completely framed. Stairs were delivered today (3/31) and are scheduled be installed Monday (4/3). In addition, the windows and sliding glass doors arrive Monday afternoon. HVAC install will also begin next week.

 

 

 

Felt and lath, or the stucco underlayment, has been installed on the North Duplex.    Our electricians have installed the recessed cans throughout. In addition, plumbing is nearly complete in both units. Stone siding has been ordered for the exterior.  Check in back next week!