There has been great progress on the Garfield Duplexes. Water lines have been installed and backfilled. They need to be connected to the large water main in Garfield Street. Front porches have also been poured!

Framers have been working hard these past two weeks, completing 2nd level framing and installing shaft wall on the North Duplex. The 3rd level lumber package was delivered this morning and framers are close to completing the shell.  Soon they will move to the south duplex to frame it.

– Lukas, Construction Manager